The following report on the Aeration Facility Project is for your information.  This report will be transmitted whenever changes occur to the operation of the aeration facility, and as a result of data monitoring of dissolved oxygen in the Stockton Deep Water Ship Channel.


Aeration Facility Weekly Update for July 26, 2010

The Aeration Facility was operated on Tuesday, July 20, 2010 to evaluate potential modifications to improve facility operational efficiencies. Confirmation of the accuracy of the oxygen flow meters and Oxyguard dissolved oxygen probes are being evaluated to confirm test results.