The following report on the Aeration Facility Project is for your information.  This report will be transmitted whenever changes occur to the operation of the aeration facility, and as a result of data monitoring of dissolved oxygen in the Stockton Deep Water Ship Channel.


Aeration Facility Weekly Update for August 23, 2010

The Aeration Facility was operated from Monday, August 9, 2010 to Thursday, August 19, 2010 with only one of the two water supply pumps to test the effectiveness of a half capacity operation. Longitudinal profiles were are completed at the beginning, middle, and end of the 10 day operational test.