The following report on the Aeration Facility Project is for your information.  This report will be transmitted whenever changes occur to the operation of the aeration facility, and as a result of data monitoring of dissolved oxygen in the Stockton Deep Water Ship Channel.


Aeration Facility Weekly Update for June 6, 2008

The Aeration Facility was not operated during the week ending June 6th. With dissolved oxygen levels continuing to approach 5.0 mg/l, the Aeration Facility may be operated the week of June 9th. Due to an electronic component failing in Pump A, the facility may be operated at only 50% capacity.  Pump A should be back in operation sometime during the week once necessary repairs are completed.