The following report on the Temporary Barriers Project is for your information and action, as appropriate.  This report will be transmitted whenever changes occur to the operation of the barriers, and as a result of modeling and/or field monitoring of water levels in the south Delta.


STATUS AS OF:   May 31, 2013


Head of Old River (HOR) Barrier:


Spring Head of Old River barrier will not be constructed in 2013. 


Agricultural Barriers (Middle River [MR], Old River near Tracy [ORT], Grant Line Canal [GLC]):


DWR received the Section 404 CWA/Section 10 RHA permit for 2013-2017 on Tuesday May 7, and construction of the south Delta temporary rock barriers started on Wednesday May 8. Construction of the Middle River barrier and Old River near Tracy barrier both started on May 8, and closure of the Middle River barrier was obtained on May 14 at approximately 2 PM.  All flap gates at MR remain tied open and construction is complete at this site.  The Old River near Tracy barrier was closed on May 30 and the Grant Line barrier is currently scheduled to be completed in mid June. Current and proposed culvert operations are below. Culverts at ORT and MR were scheduled to be released to tidal operation on June 1, 2013, but that has been postponed to Monday June 3.


Temporary Barriers Culvert Operations.jpg


Environmental Permits Compliance Reporting:


Environmental Compliance monitoring has been occurring as required. 


Middle River-- Construction is complete at this site.  A nesting pair of Swainson’s hawks have been observed on an island west of the Middle River Barrier and appear to be incubating eggs as of May 31st.  Nesting Barn Swallows were observed in one of the flap gate control boxes and was monitored until the young fledged on May 18th.  Once the young had fledged the nest was removed and the control box was covered to exclude the swallows.  No western pond turtles were observed during construction.

Old River Tracy-- A pair of nesting great horned owls was observed with young before construction on the South side of Old River, East of the barrier site, however, when construction began the nest was empty and appeared to have failed.  A nesting pair of red-tailed hawks is located on the South side of Old River across from the storage and staging area.  As of May 31st, two young have been seen in the tree outside of the nest and they should  fledge soon.  Acoustical monitoring occurred at the construction site on Monday, May 20th and Thursday, May 23rd.  No western pond turtles have been observed in the construction area, however, one has been seen sunning itself to the East of the construction area. Turbidity data was collected during the construction.

Grant Line Canal--At Grant Line Canal three pairs of nesting Swainson’s Hawks have been observed near the barrier construction site.  All three pairs have been observed incubating eggs as of May 18th and as of May 31st the two southern nests have hatched a single young and the other appears to still be on eggs.  Observations of these nests suggest that construction activities are not causing significant disturbances to the nesting pairs.  A western pond turtle was seen crossing the haul road and was allowed to cross.  Acoustical monitoring occurred at the construction site on May 24th, May 29th and May 30th. Turbidity data was collected during the construction.


Water Levels and Water Quality Notifications:


It is discovered that flap-gates at Tom Paine Slough siphons are in need of replacement. Divers removed the damaged flap gates on May 16 and 17, 2013. Replacement of the flap gates was completed on May 31, 2013.  Forecasted minimum water levels will drop below target levels at all three monitoring locations.


Modeling:


Modeling Assumptions:
Middle River barrier was closed on May 14th, Old River near Tracy barrier to be closed on May 30th, and Grantline Canal barrier to be partially closed on June 10th, 2013.  All flap-gates on the Middle River and Old River near Tracy barriers will be released to tidal operation on June 1st, 2013, Grantline Canal barrier flap-gates to stay tied open until Delta Smelt concerns have passed.

Modeling results are attached and forecasted minimum water levels will drop below target levels at all three monitoring locations.  

Water levels for the forecast period are as follows:

Middle River at Howard Road (sta MHR) – Actual low water levels are approximately 1.0 ft above the modeled forecast at 0.6 ft on May 30th.   Modeling shows low water levels will drop to approximately -0.4 ft (0.7 ft below the target of 0.3 ft) on May 31, 2013, then rebound to approximately 0.4 ft on June 14th, the end of the forecast period.

Old River at Tracy Blvd. (sta OLD)– Actual low water levels are approximating the modeled forecast at 0.2 ft on May 30th.   Modeling shows low water levels will drop to approximately 0.1 ft (0.1 ft above the target of 0.0 ft) on May 31, 2013, then rebound to approximately 0.4ft on June 14th, the end of the forecast period.

Doughty Cut (sta DGL) – Actual low water levels are approximately 0.3 ft above the modeled forecast at -0.2 ft on May 30th.   Modeling shows low water levels will drop to approximately -0.6 ft (0.6 ft below the target of 0.0 ft) on May 31, 2013, then rebound to approximately -0.2 ft on June 14th, the end of the forecast period.

 

Real-time south Delta water level data is available on CDEC at the URL below:
http://cdec.water.ca.gov/river/southdeltaStages.html 


These weekly updates are also available for your information on our website:
http://baydeltaoffice.water.ca.gov/sdb/tbp/web_pg/tempbar/weekly.cfm


We recently moved this email list to a new list server, and this is the first message to the list. The new server has enhanced capabilities.  Anyone can subscribe or unsubscribe to the list by clicking the link below:
https://listserv.state.ca.gov/wa.exe?SUBED1=DWR_TBPUPDATE&A=1

Alternatively you can contact me, and I can make additions or removals to the mailing list.


Thank you!
Jacob McQuirk, P.E.
DWR|Bay-Delta Office
Temporary Barriers and Lower San Joaquin
1416 9th St., Room 215-23
Sacramento, CA 95814
office:   916-653-9883
Fax:        916-653-6077
http://baydeltaoffice.water.ca.gov/sdb/tbp/index_tbp.cfm

 


To unsubscribe from the DWR_TBPUPDATE list, click the following link:
https://LISTSERV.STATE.CA.GOV/wa.exe?SUBED1=DWR_TBPUPDATE&A=1