Barriers

Beginning Of-Site Work

Beginning In-Water Work

Closure

Complete Removal

Spring Head of Old River March 16, 2015 March 16, 2015 April 8, 2015 June 2015
Middle River March 30, 2015 March 30, 2015 April 3, 2015 Early to Mid November 2015
Old River near Tracy March 16, 2015 March 16, 2015 April 7, 2015 Mid to Late November 2015
Grantline Canal April 2, 2015 April 2, 2015 June 2015 Mid to Late November 2015
Fall Head of Old River Sept. 2015 Sept. 2015 Sept. 2015 Mid to Late November 2015

 

 

If you have questions or comments regarding the Temporary Barriers Project, please contact Jacob McQuirk at (916) 653-9883.