The following report on the Temporary Barriers Project is for your information and action, as appropriate.  This report will be transmitted whenever changes occur to the operation of the barriers, and as a result of modeling and/or field monitoring of water levels in the south Delta.


STATUS AS OF:   June 3, 2010

Head of Old River (HOR) Barrier:

The spring Head of Old River rock barrier was not installed this season.  Instead, as in 2009, a Non-Physical Barrier (NPB) was installed.  Installation began April 5 and was completed on April 15.  The operation of the NPB supported the VAMP fish study and includes a determination of the NPB’s effectiveness.  The salmon smolt monitoring was concluded on May 26 at the end of the VAMP, however the NPB will stay in operation through June 15th  in compliance with our NMFS biological opinion to benefit non-VAMP smolts that may still be in the river.

Agricultural Barriers (Old River near Tracy [ORT], Middle River [MR], Grant Line Canal [GLC]):

Construction of the MR barrier began on May 19.  Due to equipment problems, closure of the MR barrier was delayed to May 24. All flap-gates are in the tied open position.

Construction of the ORT barrier began on May 10 and the boat ramp was completed on May 13.  Closure of ORT barrier was achieved on June 3 at 8:30 a.m. All flap-gates are in the tied open position.  However, crews have discovered slight settlement at the upstream boat ramp.  The problem will not impair boat ramp operations and settlement repair is scheduled for June 7.

The Installation of the GLC barrier will begin in mid-June after the removal of the NPB.  The GLC barrier site needs to remain open to allow passage of a large barge/crane that will be dismantling the NPB on June 16.

Modeling:

Modeling will start next week, however CDEC data was plotted and is attached. Actual water levels are at or above the trigger levels (0.0 feet MSL at Old River and Grant Line Canal barriers, 0.3 feet MSL at Middle River barrier) but will be improving since we closed the ORT barrier this morning and are approaching the next spring tide.

These weekly updates are also available for your information on our website:
http://baydeltaoffice.water.ca.gov/sdb/tbp/index_tbp.cfm


If you know of anyone else that should be receiving this update, please let me know by email, and I'll add them to the mailing list.  Thanks!

Mark A. Holderman, P.E.
Chief, Temporary Barriers Project and Lower San Joaquin
Bay-Delta Office
California Department of Water Resources
1416 9th St., P.O. Box 942836
Sacramento, CA 94236-0001
Phone: (916) 653-7429  FAX: (916) 653-6077
Cell: (916) 601-6036 E-Mail: markho@water.ca.gov