STATUS AS OF:   June 10, 2011

Head of Old River (HOR) Barrier:

The planned spring Head of Old River non-physical barrier was not installed this season due to high flows in the San Joaquin River as a result of late season storm activity and associated heavy snow pack.  High velocity posed excessively dangerous conditions for divers which ruled out the possibility of installing the necessary equipment on the channel bottom.  As a result, fish studies at the HOR have been re-structured to evaluate predatory fish behavior in the absence of a non-physical barrier.  In support of this analysis, the Fisheries Foundation is capturing and tagging predators in the HOR vicinity. The movement of VAMP and  6-yr study releases of tagged salmon smolts and steelhead are being tracked in 2 dimensions to evaluate behavior in absence of the NPB.  The final fish release for this study is scheduled for June 17, 2011.

 

Agricultural Barriers (Old River near Tracy [ORT], Middle River [MR], Grant Line Canal [GLC]):

Installation of the Old River at Tracy (ORT) barrier started on May 27, 2011 and closure was achieved today June 10, 2011.  Middle River (MR) barrier construction started on June 1, 2011 and was closed Monday June 6, 2011.  All culvert flap gates at both barriers are tied open. Installation of the ORT and MR barriers will accommodate on-going fish monitoring studies and support  water levels for south Delta diverters. The fish monitoring studies are required by the 2008 National Marine Fisheries Service (NMFS) biological opinion to: 1) examine the movements and survival of listed fish through the channels of the South Delta and ; 2) examine predation effects associated with the TBP.   DWR staff have been coordinating with VAMP to delay the fish releases intended to evaluate juvenile salmonid and predator behavior in the vicinity of the barriers.  DWR staff continue to capture and tag predators in support of this study.

Installation of the Grantline Canal (GLC) barrier will include re-construction of the south abutment and culvert structures which were removed at the end of the 2010 season.  The Grantline Canal culverts had reached the end of their service life and required replacement to provide on-going barrier effectiveness.  Construction of the GLC barrier started today Friday June 10, 2011 and will continue through early July.

Water Levels/Water Quality Problem Notifications:

None.

Modeling:

Modeling results are attached for two separate runs, one assuming no transfers and one run with transfers (JPOD).  The difference in water levels between the two runs are barely measurable.  Minimum water levels for the forecast period are approximately +1.30 feet above target levels in Middle River at Howard Road (MHR).  Following the closure of the Old River at Tracy barrier today, minimum water levels that will occur during the neap tide on June 23, 2011 are slightly over +1.0 feet above the target at Doughty Cut (DGL) and +1.25 feet at Old River at Tracy Blvd (OLD).  All water levels in general will increase as we approach the spring tide on June 15, 2011 and then decrease into the neap tide on June 23, 2011. 

These weekly updates are also available for your information on our website:
http://baydeltaoffice.water.ca.gov/sdb/tbp/web_pg/tempbar/weekly.cfm


If you know of anyone else that should be receiving this update, please let me know by email, and I'll add them to the mailing list.  Thanks!

Jacob McQuirk, P.E.
Chief, Temporary Barriers Project and Lower San Joaquin
Bay-Delta Office
California Department of Water Resources
1416 9th St., P.O. Box 942836
Sacramento, CA 94236-0001
Phone: (916) 653-9883  FAX: (916) 653-6077
Cell: (916) 425-6857 E-Mail: jacobmc@water.ca.gov